Good afternoon!  Please find below the status of work for the Allandale Storm Drain Improvements

 Last week:

  • Finalized sod placement
  • Continued watering of grass
  • Final paving occurred Thursday, August 9 through Saturday, August 11.   

Rain Days:    None

**The schedule below is projected as accurately as possible, however, all dates are subject to change due to the nature of construction and weather**

This week:

  • Wastewater manholes on Bull Creek between 2222 and White Rock will receive epoxy coating to inhibit corrosion on Wednesday, August 15. 
  • Handrail on Bull Creek should be completed by Friday, August 17
  • Striping on Shoal Creek will be completed on Friday, August 17
  • Adding topsoil and mulch to the outfall at Shoal Creek and Bull Creek.
  • Final walk through on Thursday, August 16 

Next week:

  • Curb addresses will be painted on Monday, August 20 and should take several days to complete.

Project construction contacts are:
Project Manager, George Jackson
512.974.7197
George.Jackson [Email address: George.Jackson #AT# austintexas.gov - replace #AT# with @ ]

Construction Inspector, Jim Evans
512.974.1586 (desk); 512.576.8890
James.Evans [Email address: James.Evans #AT# austintexas.gov - replace #AT# with @ ]