Storm Drainage Project Update – 07.10.12

Good afternoon!  Please find below the status of work for the Allandale Storm Drain Improvements

Completions Prior Week:

  • The final inlet was set on Nasco on Monday, July 2
  • Removed curb/gutter and driveways on north bound Nasco
  • Excavation of north-bound Nasco
  • Cast-in-place inlet top completed, inlets completed
  • Cement stabilization of north bound Nasco
  • Cut finish grade for curbs on northbound Nasco
  • Finalizing work on tributary, possibly working into next week
  • Rain Days:    None

Holiday:  No work was performed on the project on Wednesday, July 4 in observance of Independence Day.