Good morning!  Please find below the status of work for the Allandale Storm Drain Improvements

Completions Prior Week:

  • Completed all but one inlet installation
  • Completed cast-in-place hybrid inlet tops Monday, June 11
  • Set fire hydrants on Nasco Thursday, June 14 through Saturday, June 16
  • Closure of South bound Nasco will begin on Friday, June 15

Rain Days:    None
 
**The schedule below is projected as accurately as possible, however, all dates are subject to change due to the nature of construction and weather**

This week:

  • Excavation of southbound Nasco, Monday June 18-Tuesday, June 19
  • Removal of curbs and gutters and driveways south bound Nasco Monday June 18.
  • Grading the subgrade of southbound Nasco
  • Cement stabilization of southbound Nasco Wednesday, June 20
  • Setting forms for cubs and gutters on southbound Nasco on Thursday, June 21
  • Pouring and forming of curbs and gutters, south bound Nasco Friday, June 22
  • Possibly setting forms and pouring driveways on south bound Nasco on Saturday, June 23

Work next week:

If not completed on Saturday, June 23, crews will set forms and pour driveways on south bound Nasco on Monday, June 25 and Tuesday, June 26

  • Crews will backfill curbs on Monday, June 25 and Tuesday, June 26
  • The south bound side of Nasco will be primed on Wednesday, June 27
  • Switch traffic, closure of northbound Nasco beginning Thursday, June 28
  • The final inlet will be set on Nasco on Friday, June 29
  • Removal of curb/gutter and driveways of north bound Nasco will begin on Saturday, June 30

We ask again that all residents please obey traffic control signage during the construction and to not go around closures.  Failure to do so can result in traffic accidents, pushing cars or pedestrians into work zones or into trenches.  Bypassing the traffic controls endangers fellow residents and work crews.  If disregard of the traffic barricades continues, it will be necessary to ask APD to monitor the area and issue tickets to violators.  Please avoid parking your car in the work zone, as this may cause delay to the progress on the project.  Finally, please stay clear of the work zones and do not cross into the work zones.  These safeguards are established for your protection and the protection of the construction crew.  Again, safety of the citizens of Austin is our main concern, so we respectfully ask for your cooperation.

Finally, your trashcan will be moved behind the curb on the opposite side of the street during construction in your area.  If you’d like to make sure that you receive your same waste receptacle back, please label the receptacle with your street address. Crews will return the receptacle to your address at the end of the day of pickup.

Once again, thank you for working to help keep the children away from the construction area and equipment.  Information on the Allandale Storm Drain Improvements can always be found at http://www.austintexas.gov/stormdrains

Please note the new construction manager, George Jackson. Project construction contacts are:

Project Manager, George Jackson
512.974.7197
George.Jackson [Email address: George.Jackson #AT# austintexas.gov - replace #AT# with @ ]
 
Construction Inspector, Jim Evans
512.974.1586 (desk); 512.576.8890
James.Evans [Email address: James.Evans #AT# austintexas.gov - replace #AT# with @ ]
 
Michelle LoRee Frith
outreach and marketing coordinator
city of austin public works
512.974.2436
www.cityofaustin.org/publicworks