Storm Drainage Project Update – 06.28.12

Good morning!  Please find below the status of work for the Allandale Storm Drain Improvements

Completions Prior Week:

  • Excavated southbound Nasco, Monday June 18-Tuesday, June 19
  • Removed curbs and gutters and driveways south bound Nasco Monday June 18.
  • Graded the subgrade of southbound Nasco
  • Cement stabilization of southbound Nasco Wednesday, June 20

Rain Days:    None

Holiday:  No work will be performed on the project on Wednesday, July 4 in observance of Independence Day.
 
**The schedule below is projected as accurately as possible, however, all dates are subject to change due to the nature of construction and weather**

Storm Drainage Project Update – 06.19.12

Good morning!  Please find below the status of work for the Allandale Storm Drain Improvements

Completions Prior Week:

  • Completed all but one inlet installation
  • Completed cast-in-place hybrid inlet tops Monday, June 11
  • Set fire hydrants on Nasco Thursday, June 14 through Saturday, June 16
  • Closure of South bound Nasco will begin on Friday, June 15

Rain Days:    None
 
**The schedule below is projected as accurately as possible, however, all dates are subject to change due to the nature of construction and weather**

Fleas

by Wizzie Brown, Texas AgriLife Extension Service Program Specialist A proper flea management program has two parts- managing fleas on your pet and managing fleas in your environment. You may want to consult a veterinarian about flea control for your pet; there are...

City Works Academy

Neighbors, The application process has begun for the 4th annual CityWorks Academy. Please share this information with your constituents and others you believe will value from this program. Online application is available at www.austintexas.gov/cityworks Folks can also...

Chess Lessons & Tournament

Austin Kids #32 at the Northwest Recreation CenterHosted by the Austin Kids Chess ClubSponsored by the Northwest Recreation Center Time:Monday, June 25th 20126 pm – 9 pm Location:Austin Northwest Recreation Center2913 Northland Dr, Austin, TX 78757 Details: A...

Storm Drainage Project Update – 06.12.12

Good morning!  Please find below the status of work for the Allandale Storm Drain Improvements

Completions Prior Week:

  • 8” water tie in at Twin Oaks and Nasco, at Nasco and White Horse and at Cavileer and Nasco
  • Sod on White Horse has been placed at most locations
  • Inlets beginning to be set on Nasco
  • Beginning of cast-in place hybrid inlet tops
  • Utility shut outs completed

Rain Days:    None

**The schedule below is projected as accurately as possible, however, all dates are subject to change due to the nature of construction and weather**

This week:

  • Continuation of inlet installation throughout this week
  • Continuation of cast-in-place hybrid inlet tops Monday, June 11
  • Setting of fire hydrants on Nasco Thursday, June 14 through Saturday, June 16
  • Closure of South bound Nasco will begin on Friday, June 15