Good afternoon!  Please find below the status of work for the Allandale Storm Drain Improvements

Completions Prior Week:

  • Primed second Phase of White Horse
  • Traffic switch on White Horse
  • Removed curb and gutter and driveways on White Horse, street excavated to subgrade
  • Grade was cut for curb and gutter and curb and gutters were formed and poured on White Horse
  • Cement slurry mixed for White Horse
  • Concrete crew continued grouting the storm drain lines at the inlets and connections to the box culvert on White Horse
  • Pre-excavations on Cavileer and Twin Oaks and on Nasco at White Horse were performed in order for water line tie-in’s
  • Bacterial tests on water lines were conducted; bacterial tests have been passed

The schedule below is projected as accurately as possible but, all dates are subject to change due to the nature of construction and weather

Rain Days:    Tuesday, May 15

This week:

  • Friday, May 25, the south half of White Horse will be paved and White Horse will now be open for full use
  • Completion of the forming and pouring of curb and gutter on White Horse (May 21)
  • White Horse driveways poured and formed (May 21-22)
  • Curbs on White Horse being backfilled with top soil (May 22-23)
  • Completed Phase 1 priming of White Horse ((May 24)
  • Adding first 1.5” of hotmix to White Horse (May 25)
  • Water tie-in on 8” line at Nasco and White Horse (TBD)
  • Water tie-in’s on 8” line on Cavileer at White Horse (TBD)
  • Water line tie-in’s on 8” line on Twin Oaks at Nasco (TBD)
  • Inlets will begin to be set on Nasco


Note:  No construction will occur on Monday, May 28, in observance of Memorial Day

Possible Closures – dates may change to due construction needs

Tuesday, May 29, the intersection will be closed at Nasco and White Horse 
Wednesday, May 30, the intersection at Cavileer and Twin Oaks will be closed during the day

Work next week

  • Water services will be switched to new water lines on Thursday, May 31 and Friday, June 1
  • Crews will raise casting and water valves on the north and south sides of White Horse
  • White Horse will have sod placed on both the north and south sides
  • Inlets will be set on Nasco

We ask again that all residents please obey traffic control signage during the construction and do not go around closures.  Failure to do so can result in traffic accidents, pushing cars or pedestrians into work zones or into trenches.  Bypassing the traffic controls endangers fellow residents and work crews.  If disregard of the traffic barricades continues, it will be necessary to ask APD to monitor the area and issue tickets to violators.  Please avoid parking your car in the work zone, as this may cause delay to the progress on the project.  Finally, please stay clear of the work zones and do not cross into the work zones.  These safeguards are established for your protection and the protection of the construction crew.  Again, safety of the citizens of Austin is our main concern, so we respectfully ask for your cooperation.

Finally, your trashcan will be moved behind the curb on the opposite side of the street during construction in your area.  If you’d like to make sure that you receive your same waste receptacle back, please label the receptacle with your street address. Crews will return the receptacle to your address at the end of the day of pickup.

Once again, thank you for working to help keep the children away from the construction area and equipment.  Information on the Allandale Storm Drain Improvements can always be found at

Please note the new construction manager, George Jackson. Project construction contacts are:

Project Manager, George Jackson
George.Jackson [Email address: George.Jackson #AT# - replace #AT# with @ ]
Construction Inspector, Jim Evans
512.974.1586 (desk); 512.576.8890
James.Evans [Email address: James.Evans #AT# - replace #AT# with @ ]

Inspection Supervisor, Greg Weems
Greg.Weems [Email address: Greg.Weems #AT# - replace #AT# with @ ]