Good afternoon!  Following are construction updates for the next two weeks for the Allandale Storm Drain Improvements Project.
Completions Prior Week:
Installed fire hydrant between Northland and 2222 on Bull Creek
Installed fire hydrant between White Rock and 2222 on Bull Creek
Installed inlet on the corner of Bull Creek and White Rock
Installed 6 sewer services on Nasco
Please note:  The original construction schedule for this week showed work beginning Monday, January 9.  Due to rain, work has been delayed at least one day.  The dates below reflect a single “rain day”.  If the rain continues into Tuesday, January 10, each date below will slip an additional day.
Bull Creek
Inlet Installation on Bull Creek will require full closure on Bull Creek immediately North of 2222 from Tuesday, January 10 through Friday, January 13.
Additional inlet installations will occur on Bull Creek on Monday, January 16 through Wednesday, January 18.  Flaggers will be operating on Bull Creek between White Rock and White Horse on these dates.
Sewer service work from 6001 Bull Creek to 6007 Bull Creek will require a flagger operation from Tuesday, January 10 through Thursday, January 12.
Sewer line will be tested on Bull Creek from Tuesday, January 17 through Thursday, January 19.  No street closures or reductions are associated with this work.
Note that while the sewer lines are being installed and lines tested, there may be some interruption to regular services.  If this is the case, a representative will notify you.  On those possible dates, we would ask that you not take hot showers, etc between 9:00 a.m. to 4:00 p.m.  

White Rock
Crews will be placing a sewer manhole on White Rock on Friday, January 13 and Monday, January 16.  This work will require a full closure on White Rock from Bull Creek to Woodview.
White Horse
A water line is being installed on White Horse from Thursday, January 19 through Monday, January 23.  This work will necessitate a full closure of White Horse between Bull Creek and Nasco.
Sewer service work on Nasco Friday, January 20, Monday, January 23, and Tuesday, January 24 will necessitate a full closure of Nasco north of White Horse to 6307 Nasco.
Please note that there will be no weekend construction for the foreseeable future.  Thank you for working to help keep the children away from the construction area and equipment.  Information on the Allandale Storm Drain Improvements can always be found at
As always, project construction contacts are:
Project Manager, Tony Krauss
Tony.Krauss [Email address: Tony.Krauss #AT# - replace #AT# with @ ]
Construction Inspector, Jim Evans
512.974.1586 (desk); 512.576.8890
James.Evans [Email address: James.Evans #AT# - replace #AT# with @ ]
Inspection Supervisor, Greg Weems
Greg.Weems [Email address: Greg.Weems #AT# - replace #AT# with @ ]
Thank you!