All water lines on Northland and Bull Creek are complete
Two fire hydrants were put in, active water line in way.
Inlets north of White Rock on Bull Creek
Letters regarding inlet or fire hydrant installations will be hand delivered on Thursday, December 22 to those addresses where the inlets will be installed.
The crews are still installing inlets and should be finished with inlet work by the end of February. Three inlets remain on White Horse. Seven inlets remain on Nasco.
Construction crews will not work between December 23-January 3rd in observance of the holidays.

Week of December 19:
 Bull Creek
Work on Bull Creek will take place with two crews running simultaneously, working on one side of the street at a time and going in the same direction.
Work on the headwall will require a flagger operation from 5908 Bull Creek to 6000 Bull Creek
Installation of inlets will require a flagger operation on Bull Creek between White Rock and White Horse on Wednesday and Thursday
Week of January 2:
Work will commence on January 3.
Bull Creek:
Installation of the first inlet on Bull Creek will take beginning January 3.  There will be a full closure at 5901 Bull Creek, just north of 2222.  Please use detours around this area.
Please note:  Several children have been playing on or around construction equipment after construction ends. This is extremely dangerous to the children of your neighborhood. We ask that you speak to your children about the possible dangers to them and ask them to stay out of fenced construction areas, away from excavated areas and off of the construction equipment. The safety of the citizens of Austin is our first concern and we ask your assistance in making sure that construction areas are off-limits for playing or exploration.
Information on the Allandale Storm Drain Improvements can always be found at  The City of Austin websites will be changing soon and you may find yourself redirected to a very different looking web site, but the information will remain the same.  As always, the project contacts are:
Project Manager, Tony Krauss
Tony.krauss [Email address: Tony.krauss #AT# - replace #AT# with @ ]
Construction Inspector, Jim Evans
512.974.1586 (desk) or 512.576.8890
James.Evans [Email address: James.Evans #AT# - replace #AT# with @ ]
Inspection Supervisor, Greg Weems
Greg.Weems [Email address: Greg.Weems #AT# - replace #AT# with @ ]
Finally, a very special thank you to the holiday carolers who came to sing to the construction crew!