Highlights

  • We will close RM 2222 at Bull Creek Road early Saturday morning (October 29) and reopen it before Monday morning rush hour traffic. The detours will be the same as the three previous closures.
  • White Horse Trail will be closed at Nasco this week, probably starting tomorrow. White Horse should be reopened on Friday or early next week.
  • There will be closures and blocked driveways on Nasco after we finish work at the White Horse Intersection, possibly as early as Friday. It will likely take about two weeks to install the storm drain pipe on Nasco.
  • We will continue installing water service lines on Bull Creek Road. This week we will be between White Rock and White Horse.
  • Bull Creek Road is closed north of RM 2222 and two driveways are blocked. We anticipate that the road will remained closed and the driveways blocked for at least two more weeks as we connect the box culverts.

Informal Meeting
Tony Krauss, the project manager, will be on site for questions most Tuesdays at 5:30 p.m. He will be at White Horse and Nasco today.

RM 2222 at Bull Creek Road
We will close RM 2222 at Bull Creek Road early Saturday morning (October 29) and reopen it before Monday morning rush hour traffic. The detours will be the same as the three previous closures. We have finished installing the box culvert through this intersection. The remaining work is for the water line and repaving. At this point, we anticipate three more weekend closures, including the weekend of October 29.

Bull Creek Road
Bull Creek Road is now open south of RM 2222, but it is closed north of RM 2222. Two driveways are blocked. We are currently laying box culvert just north of the intersection. Afterwards we will connect the two ends of the box culvert.  We anticipate that the road will remained closed and the driveways blocked for at least two more weeks.

We are continuing to install water service lines on Bull Creek Road. This week we will be between White Rock and White Horse.

White Horse Trail
White Horse Trail will be closed at Nasco this week, probably starting on Wednesday. White Horse should be reopened on Friday or early next week. It will be closed again in about two weeks at the tributary for a few days. This closure will affect pedestrian traffic too. There will be additional closures in the upcoming weeks to install the pipe east of the tributary.

Nasco
We expect it will take about two weeks to install the storm drain pipe on Nasco. We may start as early as Friday of this week. Both lanes of the road will be closed. Driveways will be blocked during the day, but we will try to reopen them at night.

More Information
Here is a link to the web site for project:
http://www.ci.austin.tx.us/watershed/flood_allandale.htm

The main contacts for this project are:
Jim Evans, Construction Inspector
512-974-1586
James.Evans [Email address: James.Evans #AT# ci.austin.tx.us - replace #AT# with @ ]

Tony Krauss, Project Manager
512-974-7138
Tony.Krauss [Email address: Tony.Krauss #AT# ci.austin.tx.us - replace #AT# with @ ]

Greg Weems, Inspection Supervisor
512-974-1570
Greg.Weems [Email address: Greg.Weems #AT# ci.austin.tx.us - replace #AT# with @ ]